168 tons of steel structure successfully installed
9 am yesterday, with the northern section of the beltway 7 km temporarily closed to Metro Line Treasury Zhuang - International Port District station on the elevated section of steel girder erection jobs across the beltway highway official launch, which is the city's subway construction The first viaduct segments.
Field: 168 tons of steel structure successfully installed
A group of more than 80 tons of steel beams, slowly lifted by crane, Xi'an Metro Line viaduct's first start lifting steel beams. The date of completion of two groups four steel erection, weighing a total of 168 tons. Today and tomorrow, the construction workers will be in the frame into 40 cm steel deck pouring concrete, laying the foundation for the future.
"The cross on the Ring of steel concrete composite beam segment, total length of 50 meters, requires the lifting of the steel structure has three sets, six." Xian Guo workers UNRWA Corporation, said yesterday the scene using two 300 ton large car lifting, succeeded two groups 4, total weight 168 tons of steel and accurate installation to a predetermined position.
According to plan, completed this morning after the last set of steel erection, construction workers will be on the new steel erection lateral connections. Tomorrow 18:00 before construction workers in the new steel bridge erected on concrete pouring completed 40 cm.
It is understood that Treasury Zhuang Station - International Port District Station Metro Line elevated section interval, the interval has a 50 m steel concrete composite beam cross-city highway department for the previous design. As long girders, beams of high technology production requirements, must be integral lifting.
According to reports, in order to prevent the steel beam structure by gravity or under pressure after sinking, steel erection to complete the formation of certain pre-bow, to prevent their subsequent laying and future operations will occur after the force steel sink. Coupled with high precision steel structure, on-site assembly is very difficult.
Travel Tip
Limit of the northern section of the beltway closed today and tomorrow
It is reported that the construction of the roads, mainly in apricot toll station to the new build toll stations, road closures to be implemented this year and next on the 2nd day of 9:00 to 18:00, the northern section of Ring Expressway will continue to implement road closures. Construction is expected at 18:00 on the 18th after the end of the northern section of the beltway will return to normal traffic.